1 standards that do not allow for machine breakdowns or other work

1
Standards that do not allow for machine breakdowns or other work interruptions and that require peak efficiency at all times are known as:   [removed]A) budgeted standards.   [removed]B) ideal standards.   [removed]C) normal standards.   [removed]D) practical standards.     2
Solaris Company, a lounge chair manufacturer, uses a standard costing system. Each unit of a finished product contains 3 yards of cloth. However, there is unavoidable waste of 0.5 yards per unit of finished product that occurs when the cloth is cut for assembly. The cost of the cloth is $10 per yard. The standard direct material cost for cloth per unit of finished product is:   [removed]A) $5.00.   [removed]B) $25.00.   [removed]C) $30.00.   [removed]D) $35.00.     3
Fausto Company employs a standard cost system in which direct materials inventory is carried at standard cost. The company has established the following standard for the materials costs of one unit of product:

During June, the company purchased 165,000 pounds of direct material at a total cost of $1,171,500. The company manufactured 25,000 units of product during June using 151,000 pounds of direct materials. The price variance for the direct materials acquired by the company during June is:   [removed]A) $15,100 favorable.   [removed]B) $15,100 unfavorable.   [removed]C) $16,500 favorable.   [removed]D) $16,500 unfavorable.     4
Fausto Company employs a standard cost system in which direct materials inventory is carried at standard cost. The company has established the following standard for the materials costs of one unit of product:

During June, the company purchased 165,000 pounds of direct material at a total cost of $1,171,500. The company manufactured 25,000 units of product during June using 151,000 pounds of direct materials. (Note that this is the same data that was provided for the previous question.) The direct material quantity variance for June is:   [removed]A) $7,000 favorable.   [removed]B) $7,000 unfavorable.   [removed]C) $7,100 favorable.   [removed]D) $7,100 unfavorable.     5
Ortiz Company reported a favorable materials price variance and an unfavorable materials quantity variance. Based on these variances, the company’s cost accountant would most likely conclude that:   [removed]A) the actual cost per unit of materials was less than the standard cost per unit.   [removed]B) the actual usage of materials was less than the standard allowed.   [removed]C) more materials were purchased than were used.   [removed]D) more materials were used than were purchased.     6
The “standard quantity allowed” is computed by multiplying the:   [removed]A) actual input in units by the standard output allowed.   [removed]B) actual output in units by the standard input allowed.   [removed]C) actual output in units by the standard output allowed.   [removed]D) standard output in units by the standard input allowed.     7
Mochel Company employs a standard cost system in which direct materials inventory is carried at standard cost. The company has established the following standard for the direct labor costs of one unit of product:

The total factory wages for June were $800,000, 90 percent of which were for direct labor. The company manufactured 25,000 units of product during June using 32,000 direct labor hours. The direct labor rate variance for June is:   [removed]A) $16,000 favorable.   [removed]B) $16,000 unfavorable.   [removed]C) $96,000 favorable.   [removed]D) $96,000 unfavorable.     8
Mochel Company employs a standard cost system in which direct materials inventory is carried at standard cost. The company has established the following standard for the direct labor costs of one unit of product:

The total factory wages for June were $800,000, 90 percent of which were for direct labor. The company manufactured 25,000 units of product during June using 32,000 direct labor hours. (Note that this is the same data that was provided for the previous question.) The direct labor efficiency variance for June is:   [removed]A) $11,000 favorable.   [removed]B) $11,000 unfavorable.   [removed]C) $11,250 favorable.   [removed]D) $11,250 unfavorable.     9
Houghton Company maintains warehouses that stock items carried by its e-retailer clients. When one of Houghton’s clients receives an order from an online customer, the order is forwarded to Houghton. Houghton then pulls the item from the warehouse, packs it and ships it to the customer. Houghton uses a predetermined variable overhead rate based on direct labor-hours. According to the company’s records, 0.04 direct labor-hours are required to fulfill an order for one item and the variable overhead rate is $6.50 per direct-labor hour. During July, Houghton shipped 240,000 orders using 9,200 direct labor-hours. The company incurred a total of $58,880 in variable overhead costs. The variable overhead rate variance during July was:   [removed]A) $920 favorable.   [removed]B) $920 unfavorable.   [removed]C) $2,600 favorable.   [removed]D) $2,600 unfavorable.     10
Houghton Company maintains warehouses that stock items carried by its e-retailer clients. When one of Houghton’s clients receives an order from an online customer, the order is forwarded to Houghton. Houghton then pulls the item from the warehouse, packs it and ships it to the customer. Houghton uses a predetermined variable overhead rate based on direct labor-hours. According to the company’s records, 0.04 direct labor-hours are required to fulfill an order for one item and the variable overhead rate is $6.50 per direct-labor hour. During July, Houghton shipped 240,000 orders using 9,200 direct labor-hours. The company incurred a total of $58,880 in variable overhead costs. (Note that this is the same data that was provided for the previous question.) The variable overhead efficiency variance during July was:   [removed]A) $920 favorable.   [removed]B) $920 unfavorable.   [removed]C) $2,600 favorable.   [removed]D) $2,600 unfavorable.     11
(Note: Answer this question only if you are responsible for Appendix 10A.)
Mirenda Company applies manufacturing overhead costs to products on the basis of direct labor-hours. The standard cost card shows that 12 direct labor-hours are required per unit of product. For August, the company budgeted to work 360,000 direct labor-hours and to incur the following total manufacturing overhead costs:

During August, the company completed 28,000 units of product, worked 344,000 direct labor-hours, and incurred the following total manufacturing overhead costs:

The denominator activity in the predetermined overhead rate is 360,000 direct labor-hours. (Note that this is the same data that was provided for the previous question.) The fixed overhead budget variance for August is:   [removed]A) $14,000 F.   [removed]B) $14,000 U.   [removed]C) $12,800 F.   [removed]D) $12,800 U.     12
(Note: Answer this question only if you are responsible for Appendix 10A.)
Mirenda Company applies manufacturing overhead costs to products on the basis of direct labor-hours. The standard cost card shows that 12 direct labor-hours are required per unit of product. For August, the company budgeted to work 360,000 direct labor-hours and to incur the following total manufacturing overhead costs:

During August, the company completed 28,000 units of product, worked 344,000 direct labor-hours, and incurred the following total manufacturing overhead costs:

The denominator activity in the predetermined overhead rate is 360,000 direct labor-hours. (Note that this is the same data that was provided for the previous question.) The fixed overhead volume variance for August is:   [removed]A) $17,200 U.   [removed]B) $19,920 F.   [removed]C) $19,920 U.   [removed]D) $31,680 U.

Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more